Check a missing parts delivery report against this truck
Get the packing list for the whole building and the bill of lading, or BOL, for each individual flatbed. Mark which truck carries primary frames, which carries panels, and where trim and hardware cartons were placed. An order-wide list alone can make a normal staged shipment look like a shortage when the next truck is still in transit.
Before unloading, ask the plant or coordinator to clarify any ambiguous bundle label. If the BOL says accessory package without a piece count, identify what that package should contain before the site signs a clean receipt. Keep a copy of the current paperwork at the unloading point rather than inside an office trailer where the receiving crew cannot use it.
Count in a controlled landing area
Assign a receiver to check bundles as they come off the truck. Record visible labels, piece counts, and condition in the order they are unloaded. Set small cartons and trim in a separate protected location so they do not disappear beneath frame bundles or get mistaken for debris.
For a building with multiple flatbeds arriving close together, create separate landing zones or clearly tag each truck's material. A mixed pile makes it difficult to determine which load lacked a component. If a package cannot be opened safely at the truck, record its exterior count and label, then schedule a prompt detailed inventory. Do not claim that an unopened bundle contains all listed parts when the contents have not been checked.
Write the discrepancy before signing
Compare the actual unload with that truck's BOL. If a listed bundle is absent, state the item, expected count, received count, and truck on the delivery receipt before signing. Photograph the remaining load, the landing area, relevant labels, and the marked receipt. Ask the carrier's representative to acknowledge the notation through the normal handoff process.
A shortage note should be factual. Do not assign blame while the plant and other truck records are still being checked. Tell the coordinator immediately so they can compare pickup paperwork and the status of the remaining flatbeds. A late report made after a clean signature and a mixed site inventory is harder to reconcile than a clear count recorded at handoff.
How Loadhorn keeps the truck records together
Loadhorn's customer workspace holds each order, truck, document, and update in one place. The customer's coordinator can upload the BOL or a photo to the order. The "where is my building" page presents a separate status sentence for each truck, so the receiver can distinguish an absent bundle from material still assigned to another load.
Loadhorn states that damage and shortages should be noted on the delivery receipt before signing. The shipper is the claimant against the carrier if a cargo claim is needed, while Loadhorn supplies the rate confirmation, BOL, proof of delivery (POD), photos, and timeline and tracks deadlines. A location report does not prove a component was received; the signed POD and specific count record establish the delivery evidence.
Resolve the source of the missing item
After the truck leaves, reconcile the plant's loaded count with each truck's signed receipt. Check whether the part remained at the plant, was placed on a different flatbed, was unloaded into another site zone, or was listed incorrectly. Keep those possibilities open until documents and physical inventory narrow them down.
Tell the erector which material can be used and which is still unverified. A missing anchor detail or trim package may affect a different phase of construction than a missing primary frame, but the schedule decision belongs with the project team. If replacement freight is required, create a new shipment record and preserve the original shortage evidence. That keeps the recovery move from obscuring what happened on the first delivery.
Talk through the load
How Loadhorn handles it
Request a written quote with the building and delivery details, or call or email to discuss the load file.
Questions
Frequently asked questions
What should a shortage notation say?
Could the part be on another truck?
Who follows up after a shortage is documented?
Keep reading
Related guides
Pre-engineered metal building freight planning
Turn a pre-engineered metal building order into truck-by-truck packing lists, loading order, site appointments and shortage checks.
Planning a multi-truck building delivery
Coordinate multi-truck building delivery with one job file, per-truck contents and status, arrival sequence, unloading windows and receipt checks.
Bill of lading for a steel building shipment
Learn how a bill of lading identifies steel building bundles, piece counts, pickup and delivery parties, and the record needed for proof of delivery.
Freight damage claims for steel buildings
Prepare a freight damage claim for steel building frames or panels with delivery notes, photos, load records and the correct written claim details.