Put the COD freight release process in writing
Cash on delivery (COD) means the balance due at delivery, but the details are controlled by the shipper's terms, the carrier agreement, and the applicable contract. Do not assume one payment method, release rule, or collection practice fits every steel-building order.
Write down the exact balance, payee, accepted payment form, named verifier, and what happens if payment is not accepted. The receiver should know before the appointment who can answer a question. The carrier should have the same agreed instructions, rather than relying on a text message or an unwritten site practice.
Name one verifier with authority
The verifier is the shipper's person who checks the payment and authorizes release. Give the site contact the verifier's phone number and a backup contact. Make sure the verifier understands the delivery window and can respond while the truck is at the site.
Keep the verifier separate from the person unloading the material when possible. The equipment operator needs to focus on the lift plan. The receipt signer needs to inspect the delivery. A clear verifier prevents a rushed payment decision from becoming another task for people who are already managing access and unloading.
Plan for a refused release
A payment issue is not the time to invent the next step. The written terms should say whether the load stays in place, returns, or is held, and who may authorize that action. Confirm that the site understands that an unresolved release can affect timing and charges under the agreed terms.
Do not send check images or sensitive payment material through a broad group chat. Keep payment handling within the parties named in the written process. Keep the written release authorization with the order record, separate from sensitive payment material. If the site believes an amount is wrong, document the question and contact the shipper's verifier rather than asking the unloading crew to decide it.
Keep payment separate from the receipt
The delivery receipt documents the material handoff and any visible exceptions. It should still be reviewed against the bill of lading and packing information. A payment decision should not prevent the receiver from noting visible damage or a shortage clearly before signing.
Save the signed paperwork, notes, and photos in one order file. That record helps the shipper distinguish a material issue from a payment question. It also reduces confusion when several people, including the buyer, dealer, plant, and carrier dispatcher, need a factual update.
Before delivery day, run a short handoff rehearsal with the verifier and receiver. Confirm which number to call first, where the written authorization is sent, and who tells the crew that unloading may begin. This prevents a small uncertainty from putting a loaded truck, a payment question, and a work crew into the same rushed conversation.
How Loadhorn keeps COD boundaries clear
For COD orders, Loadhorn records the shipper's terms and agrees them with the carrier before the truck is booked. The carrier collects the payment the shipper specified at delivery, before unloading.
The shipper's named verifier alone authorizes release in writing, and the carrier's dispatcher confirms that decision by phone. Loadhorn never touches, holds, or approves the money and never receives check images. If release is refused, the carrier follows the written keep, return, or hold terms.
Talk through the load
How Loadhorn handles it
Request a written quote with the building and delivery details, or call or email to discuss the load file.
Questions
Frequently asked questions
What should COD freight instructions include?
Who approves release on a COD order?
Does Loadhorn handle the payment?
Keep reading
Related guides
Delivery appointment and buyer confirmation
Set a steel building delivery appointment with written buyer confirmation, a practical delivery window, site readiness and a clear day-of contact plan.
Job site delivery checklist for steel buildings
Use this job site delivery checklist to confirm access, unloading equipment, contacts and payment before steel building freight arrives.
Bill of lading for a steel building shipment
Learn how a bill of lading identifies steel building bundles, piece counts, pickup and delivery parties, and the record needed for proof of delivery.
Freight accessorial charges on steel building loads
Plan accessorial charges for steel building freight, including detention, truck ordered not used, layover, tarp pay, storage, and redelivery terms.